Onefinity Production Update 1/28/26

Date: January 28th 2026


We’re excited to share another production update on our Gen 2 CNC machines and the new Apprentice Series as we complete the final stages of preparation.


Gen 2 Elite

Batch 1 delayed due to customs hold up.


Production of the Gen 2 CNC lineup is progressing steadily, with most major components in stock. The final injection-molded parts and completed packaging has arrived at the shop.


A small number of key components (Rail Ends for example) have been delayed clearing customs by one week after arriving in Toronto. Once release is completed, production will continue, with Batch 1 of the Gen 2 Elite Series expected to begin shipping in early February 2026.


Apprentice

Batch 1 delayed due to customs hold up.


Production of the Apprentice CNC is progressing well, with mechanical and molded components already at the shop. Batch 1 of the Apprentice Series is expected to ship in early to mid-February as reported in the last update.


All parts currently on order will support the first four production batches of both the Gen 2 and Apprentice CNC models. As efficiencies improve, we expect shipping timelines for later batches to accelerate, and our team is already putting in extended hours to ensure we meet our delivery commitments.


Heavy Duty Fixed Leg Stand Kit:

Batch 1 delayed due to customs hold up.


The components for the Heavy Duty Fixed Leg Stand Kit are in Toronto but in the same shipment which is currently clearing customs. We expect production to start early February 2026.


Elite Redline Upgrade Kits:

Batch 1 Delayed due to customs hold up.


Shipments of the Elite Redline Kits are now scheduled to start Mid-February 2026.